The Real Clock · Newfoundland and Labrador

Bay du Nord

Decision issued

Checked: · This is a dated check, not a live feed.

Days on the calendar

1,336days

Start to first decision

Record start
Count ends
Share image Bay du Nord

WAKE UP CANADA

Share the case for change

Bay du Nord

Keep the source, date and notes with the image.

Checked:

wakeupcanada.ca/en/clock/bay-du-nord/
Scan to open this page
Scan this code to read the full case.

Save an image

If the image opens in a new tab, press and hold it or use your browser’s save tool.

The clocks on the public record

These are the days counted for each phase by the agency when we checked. They are not one clock. We have not checked every pause or legal change.

No day count verified for this phase. This review used the 2012 law. Current phase limits do not apply to it.

What happened

  1. Before our count starts

    First project summary filed

    Source 1 ↗

  2. Start date on the registry

    Source 1 ↗

  3. Final study rules issued

    Source 1 ↗

  4. Decision time limit extended

    Source 1 ↗

  5. Decision time limit extended

    Source 1 ↗

  6. First decision issued

    Source 1 ↗

Read this with the numbers

A decision ends this first review clock. More permits or conditions may still be needed. Listing a project does not mean we support it.

The Real Clock

What we want

Make every stage clear. Say who must act next. Explain each pause. Keep strong rules for harm and rights.

Read our case for a clear clock ↗
  1. Publish one clear record for each project.
  2. Show who must act next and by when.
  3. List each pause, its reason and who asked for it.
  4. Publish decisions and reasons on time. Keep public input and Indigenous rights.

How we count

We do not apply one two-year promise to all these projects. Listing a project does not mean we support it.

Sources

  1. Bay du Nord Development Project — Canadian Impact Assessment Registry ↗Source document in English