The Real Clock

Big projects need clear rules and a fair clock. See when each review began, what happened and what is still missing.

This first set has six projects in four provinces. It is a chosen sample, not a score for Canada.

This is a dated check, not a live feed. Listing a project does not mean we support it.

Days on the calendar

Calendar days include work by the applicant. They are not all days of government review. No late-or-on-time claim.

Ontario · Decision issued

Crawford Nickel ↗

Start to first decision

1,453 days

—

Ontario · Decision issued

Webequie road ↗

Start to first decision

2,493 days

—

Quebec · Review ended without a decision

Wasamac gold ↗

Start to end of review

1,581 days

—

British Columbia · In progress

Berg copper ↗

Start to check date

29 days

—

Quebec · Decision issued

Contrecœur port ↗

Start to first decision

1,872 days

—

Newfoundland and Labrador · Decision issued

Bay du Nord ↗

Start to first decision

1,336 days

—

We count from the start date on the federal record. The start day is not counted. The end day is counted. For an open review, we stop at the check date.

Share image The Real Clock

WAKE UP CANADA

Share the case for change

The Real Clock

Keep the source, date and notes with the image.

Checked:

wakeupcanada.ca/en/clock/
Scan to open this page
Scan this code to read the full case.

Save an image

If the image opens in a new tab, press and hold it or use your browser’s save tool.

The Real Clock

What we want

Make every stage clear. Say who must act next. Explain each pause. Keep strong rules for harm and rights.

Read our case for a clear clock ↗
  1. Publish one clear record for each project.
  2. Show who must act next and by when.
  3. List each pause, its reason and who asked for it.
  4. Publish decisions and reasons on time. Keep public input and Indigenous rights.

How we count

We do not apply one two-year promise to all these projects. Listing a project does not mean we support it.

Get the data ↓Machine-readable records keep dates, source links and limits.

Sources

  1. Crawford Nickel Project — Canadian Impact Assessment Registry ↗Source document in English
  2. Webequie Supply Road Project — Canadian Impact Assessment Registry ↗Source document in English
  3. Wasamac Gold Mine Project — Canadian Impact Assessment Registry ↗Source document in English
  4. Berg Copper Project — Canadian Impact Assessment Registry ↗Source document in English
  5. Contrecœur Port Terminal Expansion Project — Canadian Impact Assessment Registry ↗Source document in English
  6. Bay du Nord Development Project — Canadian Impact Assessment Registry ↗Source document in English
  7. Impact Assessment Act ↗Source document in English
  8. Information and Management of Time Limits Regulations ↗Source document in English
  9. Crawford Nickel Project — Impact assessment decision statement, July 31, 2026 ↗Source document in English
  10. Berg Copper Project — Public comments invited, October 8, 2026 ↗Source document in English